Attivo Trail Ankeny Phase II - February 2024
Construction progress for Phase II at Attivo Trail Ankeny has been steady during the mild winter season.
The storm sewer on the site's north side has been installed, while subgrade rock has been laid on the north drive. This will help assist in delivering precast concrete into the underground parking garage.
The underground parking garage footings are complete, and the perimeter foundation walls are almost 75% formed and poured. The basement of the parking garage has also been fitted with subgrade rock to accommodate the crane during the installation of the concrete precast.
Waterproofing of the foundation walls has begun and is 25% complete. Additionally, the foundation walls for the section of the building without a parking garage underneath have started to be formed and poured.
The concrete foundation work should be completed by February, and precast concrete panels will be delivered and set starting in March.
Phase II includes 142 units, a theater, an additional outdoor courtyard, and an indoor gathering space. This phase also adds approximately 71 underground parking spaces and 62 garages. The phase II construction team will deliver 88 out of 142 units in early summer 2025 and the remaining 54 units in fall 2025.