The Emory North Liberty - April 2024
Site paving is done, sidewalks are 65% complete, and landscaping will start soon.
The 44 Plex building's first floor has been painted. Doors, trim, and flooring have been installed on the upper floors. About 30% of the MEP trim out is done.
In the 52A Plex, drywall is being hung on the 4th floor, and MEP rough-ins are happening on the 3rd floor.
The final touches are being made on framing and roofing for the 52B Plex. MEP Rough-Ins will begin after the 52A Building is completed.
The most significant steps in construction have been in the Clubhouse. The state-of-the-art golf simulator's first phase is installed. Painting, ceramic tile, and light fixture installation are underway, and the flooring will start soon.
Stay tuned for more updates as the Emory North Liberty project progresses.