The Emory North Liberty - February 2024
As temperatures rise, so does the anticipation for the near completion of the first phase of The Emory North Liberty. The first building is expected to open at the beginning of July.
CONSTRUCTION UPDATES
GENERAL SITEWORK
The paving on site is about 90% complete, and all the underground utilities have been installed. Construction on the swimming pool is about to begin.
CLUBHOUSE
The framing for the clubhouse is done, and the lower windows and roof are now in place. The Mechanical, Electrical, and Plumbing (MEP) trades are in the final stages of their rough-ins for the building, with drywall installation anticipated to start soon. Additionally, the siding and masonry work for the building is scheduled to begin in the next few weeks.
44 UNIT BUILDING – 1255 EMORY PLACE
The exterior masonry work for the building is nearing completion, and siding installation commenced in mid-February. The fourth floor has been drywalled, taped, finished, and ready for the painting phase.
The drywalling process is finished on the third floor, and taping and finishing work are underway. The second floor is now set for drywall installation, while the first floor has completed the MEP rough-ins and is awaiting inspection.
52B BUILDING – 1265 EMORY PLACE
The building has been completed and framed, with windows already installed. Roof installation has started, and the MEP trades are just beginning their rough-ins for this structure.
52A BUILDING – 1275 EMORY PLACE
Over 95% of the framing is complete, with Tyvek and window installation beginning soon.
MAINTENANCE BUILDING & GARAGES
The maintenance building and garages have been framed, with roofs installed on the maintenance building and two out of the four garages. Siding and masonry work on the building is scheduled to begin this month.